
Progress Claims and Variations Perth
Accurate progress claims and variation pricing prepared against the contract to protect your margin. Perth residential and commercial builders and subbies.
- 18+ years experience
- First estimate free
- 24hr turnaround
- No lock-in contract
Where Builders Lose Margin
Progress claims and variations are where a lot of Perth builders and subbies lose margin without realising it. A claim that is poorly documented gets reduced. A variation that is priced off the cuff gets disputed and whittled down. A delay that is not formally notified loses its entitlement to an extension of time.
We prepare progress claims and variation submissions for Perth builders and subcontractors, priced against the contract, backed by evidence and written in a way that is hard to dispute.

Progress Claim Preparation
A progress claim under an AS 2124, AS 4000 or HIA/MBA contract needs to demonstrate the value of work completed to date and compare it to amounts previously certified and paid. Getting that structure right matters because a poorly presented claim gives the superintendent a reason to certify a lower value.
| Claim Component | What It Contains | Why It Matters |
|---|---|---|
| Completed works value | % complete by trade item against BoQ or schedule of rates | Basis for certification, must be defensible |
| Previously certified | Prior payment certificates and amounts paid | Reconciliation prevents double-claiming or missing claimed amounts |
| Variations claimed | Approved and unapproved variations by item | Separating variation from contract sum is essential |
| Retention release | Retention amount held and release milestones | Practical completion triggers retention release under most contracts |
| Delays and EOTs | Extension of time notifications if relevant | Failure to notify within contract timeframe loses entitlement |
| Materials on site | Plant and materials stored on site but not yet incorporated | Allowed under some contracts with delivery evidence |
What Is a Progress Claim?
A progress claim is a formal request for payment for work completed during a specified period, submitted under the terms of a construction contract. In Western Australia, progress claims on construction projects over a threshold value are also regulated under the Building and Construction Industry (Security of Payment) Act 2021. A correctly prepared progress claim establishes the claimable amount and creates the contract mechanism for payment.
Evidence Beats Opinion
Most claims get cut back for the same reason. The claim says a trade is eighty per cent complete and there is nothing in the document showing why that is the right number.
Assess it against the bill of quantities instead and the conversation changes. You are no longer arguing about a feeling, you are pointing at measured work that either exists on site or does not.
What Goes in with the Claim
- Percentage complete assessed line by line against the BoQ
- Dated site photographs of the work being claimed
- Materials on site listed and valued separately
- Approved variations shown as their own items
- Retention and previous certifications carried correctly
- Delivery dockets and supplier invoices where relevant
- The contract clause the claim is made under
- A clean running total that reconciles to the last claim

BoQ
Assessed against
Line by line
SOPA
WA payment framework
Claims prepared to suit
24hr
Usual turnaround
Straightforward claims
Free
First job
No lock-in contract

The Money Is Lost Before the Argument Starts
By the time a claim is in dispute, the damage is usually months old. The variation was done on a nod, the delay notice was never sent, the extra work was never priced.
None of that is recoverable by arguing harder at the end. It is recoverable by writing it down at the time, in the form the contract asks for, while everyone still agrees on what happened.
That is the habit we are really selling here. The paperwork is not admin, it is the only version of events that survives once the job is finished.
Variation Pricing and Submission
Variations are where margin is made or lost on a construction project. An instruction from the principal, architect or engineer to carry out work outside the contract scope is a variation entitlement. Getting it priced and submitted correctly determines whether you recover the full cost.
What Makes a Variation Submission Hold Up
- Written instruction or direction from the principal, architect or superintendent
- Clear description of the varied work and how it differs from the contract scope
- Quantities measured from the direction or marked-up drawings
- Labour, material and plant rates consistent with the contract or with current market evidence
- Margin and overhead allowance stated separately if the contract allows it
- Submission within the timeframe specified in the contract
- Reference to the relevant contract clause authorising the variation
WA
SOP Act 2021
Payment protection
Contract
Clause references
AS 2124 / AS 4000 / HIA
Priced
Market rate evidence
Defensible claim
24hr
Response
Most queries
Extension of Time Claims
A delay caused by the principal, architect or unforeseen conditions may entitle you to an extension of time under the construction contract. The entitlement is only preserved if you notify within the timeframe specified in the contract, which is often 14-28 days from the delay event.
We prepare extension of time notices and delay cost claims for Perth builders and subbies, identifying the entitlement, quantifying the delay impact and presenting the claim in a format that meets the contract requirements.
Notice Periods: Miss Them and You Lose the Entitlement
Most construction contracts in WA require a written delay notice within 14-28 days of the delay event. If you do not give notice in time, you may lose the right to an extension of time regardless of how genuine the delay was. Talk to us early if a delay is occurring, not after the program has slipped by six weeks.
- 01
Contract and Documents Reviewed
We review the contract, the original program and the delay event documentation to confirm the entitlement basis.
- 02
Delay Quantified
Delay impact on the critical path measured from the program. We identify which activities were affected and by how long.
- 03
Costs Calculated
Delay costs calculated against the contract rates or current WA market, covering extended preliminaries, additional supervision and plant standing time.
- 04
Claim Drafted
Extension of time notice and delay cost claim drafted with contract clause references and supporting evidence.
- 05
Submitted for Review
We deliver the claim for your review before submission. You know what we are claiming and why before it goes to the superintendent.
Common Questions
Straight answers on how we price progress claims and variations in Perth. If yours is not here, send your plans and just ask.
The Building and Construction Industry (Security of Payment) Act 2021 provides a rapid adjudication process for payment disputes on construction projects in Western Australia. It allows a claimant to serve a payment claim and, if the respondent does not pay or provides a payment schedule that disputes the amount, to refer the dispute to adjudication. We prepare the payment claim documentation, the adjudication itself is a legal process.
Yes. If a principal or superintendent has certified a lower amount than claimed, we can review the payment schedule, identify the disputed items and prepare the supporting documentation to respond to the dispute.
Yes, but it is harder. A variation priced before the work starts has more credibility than one priced from a reconstruction after the fact. If the work is already done, we price it from whatever evidence is available, site photos, delivery dockets, labour timesheets, and we are clear about where the evidence is strong and where it is not.
Yes. Most of our variation work is for subcontractors, bricklayers, concreters, plasterers and tilers whose contract is with the head contractor, not the principal. The process is the same, identify the instruction, quantify the work, price it correctly and submit it in time.
Get Your First Estimate Free
Send us your plans and we will take it from there. First job is on us, 24-hour turnaround on most residential jobs, and no lock-in contract.



